Washington Court Denies Subcontractor’s Claim Based on Contractual Change and Notice Provisions
January 29, 2024 —
Wendy Rosenstein - Ahlers Cressman & Sleight PLLCThe recent unpublished case, Cascade Civil Construction, LLC v. Jackson Dean Construction, Inc., et al.,[1] provides a legal justification for contractors to require a directive or change order in advance of performing changed work—thereby preventing the party who requested the changed work from later arguing that notice provisions were not complied with.
In the case, Jackson Dean, the prime contractor, hired Cascade to perform excavation work on a project to build a new Costco Corporate headquarters. Due to the Covid-19 pandemic and other issues, Jackson Dean directed resequencing, which required Cascade to perform excavation concurrent to dewatering. Jackson Dean also required deeper-than-planned excavation under one of the buildings.
Read the full story...Reprinted courtesy of
Wendy Rosenstein, Ahlers Cressman & Sleight PLLCMs. Rosenstein may be contacted at
wendy.rosenstein@acslawyers.com
Meet the Forum's ADR Neutrals: LISA D. LOVE
March 19, 2024 —
Marissa L. Downs - The Dispute ResolverCompany: JAMS
Office Location: New York, NY
Email: llove@jamsadr.com
Website: https://www.jamsadr.com/love/
Law School: Georgetown University Law Center (J.D. 1984)
Types of ADR services offered: Arbitration, mediation, neutral evaluation and special master services
Affiliated ADR organizations: JAMS, Chartered Institute of Arbitrators, and CPR
Geographic area served: Domestic and International
Q: Describe the path you took to becoming an ADR neutral.
A: I started my legal career practicing law as a complex commercial transactions attorney in the corporate department of a major New York law firm for eleven years. After leaving the firm, I served as chief legal counsel to several municipalities and as co-founding partner of a boutique finance, infrastructure and real estate law firm.
Read the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Appraisal Can Go Forward Prior to Resolution of Coverage Dispute
April 08, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Florida Supreme Court found that a trial court could compel an appraisal of the insured's loss prior to resolving coverage issues. Am. Coastal Ins. Co. v. San Marco Villas Condo. Ass'n, Inc., 2024 Fla. LEXIS 185 (Fla. Feb. 1, 2024).
Hurricane Irma damaged San Marco Condominium Association's buildings. American Coastal paid $192,629.75 for the loss. San Marco estimated the damage to be in excess of eight million dollars. San Marco demanded an appraisal under the policy. American Coastal refused to submit to appraisal because it was premature as its investigation was still ongoing.
San Marco sued American Coastal and asked the court to compel appraisal. American Coastal argued that San Marco had committed fraud or had made material misrepresentations regarding its claim. The trial court heard San Marco's appraisal motion and entered an order compelling appraisal. American Coastal appealed, bu the Second District Court affirmed.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Denial of Motion to Dissolve Lis Pendens Does Not Automatically Create Basis for Certiorari Relief
November 16, 2023 —
David Adelstein - Florida Construction Legal UpdatesA recent appellate decision out of Florida’s Sixth District Court of Appeal holds that a trial court’s denial of motion to dissolve a lis pendens does NOT automatically give a basis for a petition for a writ of certiorari. Generalized allegations of “irreparable harm” to support the basis for the petition for writ of certiorari are insufficient. Rather, the party moving for the petition MUST clearly demonstrate the irreparable harm; otherwise, the petition for writ of certiorari will fail.
A lis pendens has legal significance. It is a recorded document that notifies the world that there is a pending lawsuit dealing with the real property at issue. This is important because who wants to buy a piece of property that is subject to litigation – that would be a risky transaction!
In CPPB, LLC v. Taurus Apopka City Center, LLC, 48 Fla.L.Weekly D1837a (Fla. 6th DCA 2023), a dispute arose as to a real estate transaction. The owner sold a parcel to a buyer. The owner also owned three adjacent parcels. As part of the transaction, the buyer agreed to perform certain improvements to all of the parcels including those adjacent parcels owned by the owner. The owner deposited funds in escrow for purposes of its share of the improvements. A payment dispute arose regarding the improvements and the buyer sued the seller. The seller filed a counterclaim to rescind the transaction along with a recorded lis pendens on the parcel purchased by the buyer. The buyer moved to dissolve the lis pendens which the trial court denied. This prompted the appeal – a petition for a write of certiorari based on the trial court’s denial of the motion to dissolve the lis pendens.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Residential Contractors, Be Sure to Have these Clauses in Your Contracts
December 23, 2023 —
Christopher G. Hill - Construction Law MusingsI have often “mused” on the need to have a good solid construction contract at the beginning of a project. While this is always true, it is particularly true in residential contracting where a homeowner may or may not know the construction process or have experience with large scale construction. Often you, as a construction general contractor, are providing the first large scale construction that the homeowner has experienced. For this reason, through meetings and the construction contract, setting expectations early and often is key.
As a side note to this need to set expectations, the Virginia Department of Professional and Occupational Regulation (DPOR) and the Virginia General Assembly require certain clauses to be in every residential construction contract. DPOR strictly enforces these contractual items and failure to put them in your contracts can lead to fines, penalties and possibly even revocation of a contractor’s license.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Appraisal Panel Can Determine Causation of Loss under Ohio Law
February 19, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the insured's motion to compel an appraisal that would include a determination of causation of the loss. Eagle Highland Owners Association v. State Farm Fire and Casualty Co., 2023 U.S. Dist. LEXIS 220937 (S.D. Ohio Dec. 12, 2023).
Plaintiff argued its property suffered wind and hail damage from a storm on June 18, 2021. A claim was submitted to State Farm. State Farm's investigation determined the loss to be $0.00. Plaintiff's investigator determined the loss to be $586,647.08 in repair costs.
State Farm opposed appraisal because, in its view, the damage arose from a loss in 2019, not from the June 18, 2021 storm. Plaintiff submitted a loss claim in 2019 for damage that State Farm alleged was exactly the same as the damage alleged in the loss claim for the June 18, 2021 storm. Therefore, State Farm did not view the matter as a dispute over an amount of loss, but rather over whether a loss even occurred on June 18, 2021.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
See the Stories That Drew the Most Readers to ENR.com in 2023
January 16, 2024 —
C.J. Schexnayder - Engineering News-RecordAs construction's very busy and eventful year nears its close and the sector awaits many more ups and downs in 2024, ENR offers a look back at the Top 20 news stories that most caught readers' attention across a broad market spectrum—from the construction start of the long-awaited $16 billion New York-New Jersey rail tunnel rebuild and winners shortlisted for the first $7 billion in U.S. government funds for developing clean-energy hydrogen hubs to the still unfolding legal battle over Las Vegas Sphere project complexities and why a Texas jury awarded $860 million in a fatal Texas crane collapse verdict.
Reprinted courtesy of
C.J. Schexnayder, Engineering News-Record
Mr. Schexnayder may be contacted at schexnayderc@enr.com
Read the full story...
HB24-1014: A Warning Bell for Colorado Businesses Amid Potential Consumer Protection Changes
February 26, 2024 —
Jennifer Brockel - Colorado Construction Litigation BlogHB24-1014 stands to eliminate the longstanding public impact requirement found within C.R.S. § 6-1-105(2) of the Colorado Consumer Protection Act (“CCPA”). While this proposed change professes the noblest intentions of “public peace, health or safety,” its effect portends a large detriment to Colorado business and an astronomical payday for Colorado plaintiffs’ attorneys.
Brief History
For over 100 years, Colorado recognized the need to protect its citizens from deceptive trade practices through a mechanism akin to the Federal Trade Commission Act that preceded it. In 1915, Colorado passed legislation prohibiting “untrue, deceptive, or misleading” advertising. C.L. 1921 § 6942 evolved into the broader protections afforded in the more recent consumer protection law from 1969 that prohibited “deceptive trade practices, and included protections from unfair, unconscionable, and deceptive acts or practices.”
Read the full story...Reprinted courtesy of
Jennifer Brockel, Higgins, Hopkins, McLain & Roswell, LLCMs. Brockel may be contacted at
brockel@hhmrlaw.com