Quick Note: October 1, 2023 Changes to Florida’s Construction Statutes
November 13, 2023 —
David Adelstein - Florida Construction Legal UpdatesEffective October 1, 2023, there were changes to Florida’s statutory scheme dealing with construction projects. This includes Florida’s Lien Law. A copy of these changes can be found below which identify additions in blue and deletions with strikethroughs. No different than before, if you have questions or concerns as to your statutory rights on a construction project, do the prudent thing, consult a construction lawyer. A construction lawyer can help you understand changes to the applicable statutory scheme or how the statutory scheme pertains to your rights. This is important because you want to make sure you understand statutory changes that apply to your work and rights.
A noteworthy change, bolded in blue below, is that there is now a basis to lien for a contractor performing construction management services “which include scheduling and coordinating construction and preconstruction phases for the construction project, or who provides program management services”:
Fla. Stat. s. 713.01 (8) “Contractor” means a person other than a materialman or laborer who enters into a contract with the owner of real property for improving it, or who takes over from a contractor as so defined the entire remaining work under such contract. The term “contractor” includes an architect, landscape architect, or engineer who improves real property pursuant to a design- build contract authorized by s. 489.103(16). The term also includes a licensed general contractor or building contractor, as those terms are defined in s. 489.105(3)(a) and (b), respectively, who provides construction management services, which include scheduling and coordinating preconstruction and construction phases for the construction project, or who provides program management services, which include schedule control, cost control, and coordinating the provision or procurement of planning, design, and construction for the construction project.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
No Damages for Delay May Not Be Enforceable in Virginia
January 08, 2024 —
Christopher G. Hill - Construction Law MusingsAnyone who reads Construction Law Musings with any regularity (thank you by the way) knows that the contract is king in most instances here in Virginia. Any commercial construction subcontractor in Virginia is likely also very familiar with so-called “no damages for delay” clauses in construction contracts. These clauses essentially state that a subcontractor’s only remedy for a delay caused by any factor beyond its control (including the fault of the general contractor), after proper notice to the general contractor, is an extension of time to complete the work. However, in 2015 the Virginia General Assembly passed a change in the law that precluded the diminishment of any right to claims for demonstrated additional costs prior to payment. This left open the question as to which types of “diminishment” would be barred by the statute.
The recent case out of the Eastern District of Virginia federal court, Strata Solar LLC v. Fall Line Construction LLC, added a bit of clarity.
Read the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Best Practices: Commercial Lockouts in Arizona
March 19, 2024 —
Patrick Tighe - Snell & Wilmer Real Estate Litigation BlogIf a tenant defaults under a commercial lease, Arizona law permits the landlord to re-take possession of the premises by locking out the defaulting tenant. However, if the landlord’s lockout is wrongful, the landlord may be liable for the damages the tenant sustains because of the wrongful lockout. To minimize such liability, here are some general best practices to follow when locking out a defaulting tenant:
- Do Not Breach the Peace. It is vital when performing a lockout to not breach the peace. What constitutes a “breach of the peace” depends on the particular circumstances at hand. For example, if a tenant arrives during the lockout and becomes angry or threatens violence, the landlord should stop performing the lockout and return at a later time. As a general rule of thumb, it is best to perform lockouts in the early morning hours or in the late evening hours when the landlord is less likely to encounter the tenant.
- Provide A Notice of Default. Many commercial leases require the landlord to provide a notice of default before the landlord can lock out a defaulting tenant. Check, double check, and triple check that the landlord followed the lease’s notice of default provisions correctly, including that the landlord sent the notices to all required parties in accordance with the time requirements set forth in the lease.
Read the full story...Reprinted courtesy of
Patrick Tighe, Snell & WilmerMr. Tighe may be contacted at
ptighe@swlaw.com
Judge Who Oversees Mass. Asbestos Docket Takes New Role As Chief Justice of Superior Court
January 02, 2024 —
Lewis Brisbois NewsroomBoston, Mass. (December 13, 2023) - Judge Michael Ricciuti, who presides over the Massachusetts state asbestos litigation docket, has been appointed to a new role as Chief Justice of Massachusetts Superior Court, effective December 22, 2023. The appointment is expected to result in the end of his tenure overseeing the state asbestos litigation.
Judge Ricciuti was appointed by Governor Charlie Baker to the Superior Court in 2017. He has served in five counties and serves six-month rotations in the Business Litigation Session, in addition to his role overseeing the Massachusetts Asbestos Litigation docket. His current committee participation includes serving on the Superior Court Judicial Education Committee and the Supreme Judicial Court Advisory Committee on Massachusetts Evidence Law. He also serves as a judicial mentor.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Contractors Battle Bitter Winters at $11.8B Site C Hydro Project in Canada
October 30, 2023 —
Jonathan Keller & Scott Blair - Engineering News-RecordHalf the year spent in bone-aching cold. Soils frozen hard as concrete. Mountains of snow. A seemingly unending flow of machinery, workforce and earthen material to and from the site. A temporary city to house thousands of workers for nearly a decade. Wildfires encroaching dangerously close. Working under the ever-watchful eyes of regulators, stakeholders and environmentalists.
Reprinted courtesy of
Jonathan Keller, Engineering News-Record and
Scott Blair, Engineering News-Record
Mr. Keller may be contacted at kellerj@enr.com
Mr. Blair may be contacted at blairs@enr.com
Read the full story...
Enforceability of Contract Provisions Extending Liquidated Damages Beyond Substantial Completion
April 15, 2024 —
Stu Richeson - The Dispute ResolverThis post takes a look at the enforceability of contract provisions providing for liquidated delay damages after substantial completion. Typically, the assessment of liquidated delay damages ends at substantial completion of a project. However, various standard form contracts, including some of the ConsensusDocs and EJCDC contracts, contain elections allowing for the parties to agree on the use of liquidated damages for failing to achieve substantial completion, final completion, or project milestones. The standard language in the AIA A201 leaves it up to the parties to define the circumstances under which liquidated damages will be awarded.
Courts are split on the enforceability of provisions that seek to assess liquidated damages beyond substantial completions. Courts in some jurisdictions will not impose liquidated damages after the date of substantial completion on the ground that liquidated damages would otherwise become a penalty if assessed after the owner has put the project to its intended use. Perini Corp. v. Greate Bay Hotel & Casino, Inc., 129 N.J. 479, 610 A.2d 364 (1992). When the terms are clear, other jurisdictions will enforce contract terms providing for liquidated damages until final completion, even if the owner has taken beneficial use of the facility. Carrothers Const. Co. v. City of S. Hutchinson, 288 Kan. 743, 207 P.3d 231 (2009).
Read the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
BWB&O is Recognized in the 2024 Edition of Best Law Firms®!
November 16, 2023 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is honored to announce the firm has been recognized for its fourth consecutive year in the 2024 edition of Best Law Firms® and is ranked by Best Lawyers® regionally in three practice areas. To read the publication, please click
here.
Regional Tier 1
Las Vegas: Litigation – Construction
Orange County: Litigation – Construction
Regional Tier 2
Orange County: Family Law
Regional Tier 3
Orange County: Commercial Litigation
Read the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Surety Trends to Keep an Eye on in the Construction Industry
March 25, 2024 —
Oliver Craig - Construction ExecutiveReflecting on the dynamics of the 2023 construction and surety industries, it is evident that opportunities and challenges have emerged for contractors that will shape the landscape for the year ahead. Contractors can not only capitalize on these trends but protect the successful companies they have already built.
PROJECT OPPORTUNITIES
There has been a notable increase in public works opportunities, driven by increased government spending and the aging infrastructure in the United States. This trend is expected to continue in 2024 and beyond, with a notable portion of work coming in transportation- and public-utility-related infrastructure.
Due to increased spending, many contractors are reporting historically high backlogs—and that often includes the largest project their company has contracted in their history. While increased spending presents more opportunity, it’s critical contractors be even more diligent about new opportunities, giving additional consideration to the following:
Job Selection: New geographies, scope, project owners and/or subcontractor relationships commonly come with a learning curve. With the current state of the market, it’s not the ideal time to be learning costly lessons. Contractors should focus on having a proactive go/no-go strategy when reviewing potential projects to identify risks early and plan accordingly.
Reprinted courtesy of
Oliver Craig, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...