No Coverage Under Installation Policy When Read Together with Insurance Application
January 16, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent case out of the Eleventh Circuit denied an underground contractor’s claim under what appears to be a commercial property installation floater policy (inland marine coverage) that covers the contractor’s materials. Whereas a builder’s risk policy is more expansive, an installation floater is narrower and can provide protection to a contractor for materials and equipment in transit, stored, or being installed subject to the terms of the installation floater policy. It can provide coverage to a trade subcontractor for materials that aren’t covered by builder’s risk.
In Travelers Property Casualty Company of America v. Talcon Group, LLC, 2023 WL 8798053 (11th Cir. 2023), an underground utility contractor that had a general contractor’s license had an installation policy that provided coverage “only for underground utility operations and the site development work tied to those operations.” Talcon Group, supra, at *1. The utility contractor was constructing two residential homes that was on land owned by an affiliated family entity. During construction of the residential homes, a wildfire destroyed the homes prior to the issuance of certificates of occupancy. The utility contractor submitted a notice of loss to its insurance carrier that provided the installation policy. The carrier denied the claim because the construction of the homes was NOT the same type of work as the installation of underground utilities which was covered. An insurance coverage lawsuit ensued.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Connecticut’s New False Claims Act Increases Risk to Public Construction Participants
April 02, 2024 —
Fred Hedberg & William Stoll - Construction Law ZoneAfter several decades, Governor Ned Lamont signed a bill into law, effective July 1, 2023, An Act Concerning Liability for False and Fraudulent Claims, Public Act No. 23-129, eliminating language that previously limited enforcement of Connecticut’s False Claims Act to claims relating to a state-administered health or human services program. The revisions dramatically expanded potential liability under the False Claims Act, allowing both private citizens and the Attorney General to bring actions under the Act in any context, including the construction industry. Consequently, contractors, subcontractors, suppliers and design professionals on public construction projects in Connecticut must be familiar with this newly enacted law and take steps to reduce the risks of doing business on such projects.
Reprinted courtesy of
Fred Hedberg, Robinson & Cole LLP and
William Stoll, Robinson & Cole LLP
Mr. Hedberg may be contacted at fhedberg@rc.com
Mr. Stoll may be contacted at wstoll@rc.com
Read the full story...
First Circuit Limits Insurers’ Right to Recoup Defense Costs or Settlement Payments
April 02, 2024 —
Eric Hermanson, Austin Moody & Victoria Ranieri - White and Williams LLPWeighing in on an issue that has divided courts nationwide, the U.S. Court of Appeals for the First Circuit has ruled that an insurer under Massachusetts law has no right to recoup defense costs, or amounts the insurer pays in settlement – even if the insurer reserves rights prior to payment and obtains a ruling, after the fact, that no defense or indemnity was owed. Berkley Natl. Ins. Co. v. Atlantic-Newport Realty LLC, No. 22-1959, 2024 U.S. App. LEXIS 4115 (1st Cir. Feb 22, 2024) (“Granite Telecomm"). However, the First Circuit rested its ruling on narrow procedural grounds, which may prolong the controversy rather than resolve it.
The insureds in Granite Telecomm owned a company cafeteria. They were sued by a food service worker who suffered a foot infection after being exposed to bacteria during a sewage backup. They sought coverage from their insurer, Berkley. Berkley argued that coverage was barred by a fungus and bacteria exclusion in the policy. The insureds disagreed. They threatened suit under M.G.L. ch. 93A, and demanded that Berkley defend the case.
Reprinted courtesy of
Eric Hermanson, White and Williams LLP,
Austin Moody, White and Williams LLP and
Victoria Ranieri, White and Williams LLP
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Ms. Ranieri may be contacted atranieriv@whiteandwilliams.com
Read the full story...
Top 10 OSHA Violations For The Construction Industry In 2023
February 26, 2024 —
Dominic Donato & Jeff Miragliotta - Kahana FeldEvery year, the Occupational Safety and Health Administration (OSHA) publishes their top violations in the construction industry. And typically, the most common violations are consistent year after year. What separates 2023 is the number of citations involving Fall Protection, Scaffolding, Ladders, and the failure to use personal protective equipment (PPE) or other life safety equipment (LSE). The following is the list of the Top Ten OSHA violations for 2023:
(10) Toxic and Hazardous Substances. There were 382 citations issued for “hazardous communication” and improper warnings issued to construction employees.
(9) Excavations. There were 395 citations issued for failure to provide proper and specific excavation requirements and instructions.
(8) Scaffolding – Aerial Lifts. There were 481 citations issued for improper lifting equipment and supports for building scaffolding.
Reprinted courtesy of
Dominic Donato, Kahana Feld and
Jeff Miragliotta, Kahana Feld
Mr. Donato may be contacted at ddonato@kahanafeld.com
Mr. Miragliotta may be contacted at jmiragliotta@kahanafeld.com
Read the full story...
Carbon Sequestration Can Combat Global Warming, Sometimes in Unexpected Ways
April 02, 2024 —
Michael S. McDonough, Robert A. James & Amanda G. Halter - Gravel2Gavel Construction & Real Estate Law BlogWhether by land, by sea or through human innovation, carbon sequestration is likely coming to (or already happening in) a destination near you. As our planet, overdosed on greenhouse gases, battles climate disasters, a logical solution is to simply stop pumping carbon dioxide into the air. Legislation worldwide is aimed at that target, but reducing output alone may not be enough. There are still billions of tons of extra CO2 already in the atmosphere—this crossroads is where sequestration comes into play.
Carbon sequestration is exactly what it sounds like—the storage of CO2. Once carbon is sucked out of the air, or in some cases pulled directly from industrial smokestacks, sequestration can be undertaken in a lot of different ways. Carbon storage happens naturally, when forests and oceans absorb and convert CO2 into organic matter, but carbon dioxide can also be artificially injected into deep underground rock formations (or wells), or in some cases technological approaches repurpose carbon into a resource like concrete, or as a catalyst in a closed-loop industrial system. However it’s accomplished, the point of sequestration is to stabilize carbon and ensure it doesn’t creep back into our atmosphere. Researchers, like those at the United Nations’ Intergovernmental Panel on Climate Change, now say that CO2 removal is vital to keeping global warming to 1.5 degrees Celsius (past that threshold, climate change could reach catastrophic levels). A 2023 University of Oxford study estimated that, currently, about two billion metric tons of carbon dioxide are being removed each year, primarily through land management (i.e., planting trees), and suggested that we need to double that amount to avoid dangerous global warming levels.
Reprinted courtesy of
Michael S. McDonough, Pillsbury,
Robert A. James, Pillsbury and
Amanda G. Halter, Pillsbury
Mr. McDonough may be contacted at michael.mcdonough@pillsburylaw.com
Mr. James may be contacted at rob.james@pillsburylaw.com
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Read the full story...
Building 47 Bridges in Two Years
December 23, 2023 —
Dan Sopczak - Construction ExecutiveEvery construction project has its challenges, but some truly push the boundaries of what is achievable in the heavy civil industry. When the Indiana Department of Transportation sought to modernize its I-65/I-70 North Split Interchange in Indianapolis, Indiana, its request for proposals included building 47 new bridges and rehabilitating six additional bridges on an ambitious two-year timeline—905 days to substantial completion.
“Three design-build teams responded to the RFQ, and the same three teams responded to the RFP,” according to INDOT Strategic Communications Director Natalie Garrett. “Proposals were scored and evaluated using the best-value evaluation process defined by INDOT. The score was a combination of a technical proposal score and a price score.”
Reprinted courtesy of
Dan Sopczak, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the full story...
Jason Feld Awarded Volunteer of the Year by Claims & Litigation Management Alliance
April 15, 2024 —
Linda Carter - Kahana FeldOn April 3, 2024, Kahana Feld’s Co-Founding Partner, Jason Feld was honored by the Claims & Litigation Management Alliance (CLM) with the Inaugural Volunteer of the Year award.
The CEO of CLM, Ronna Ruppelt stated, “The new CLM Volunteer of the Year award honors dedicated members who passionately serve the CLM community. Jason’s service spans over a decade as both the President and Director of Events for the Orange County Chapter. Under his guidance, this chapter has flourished – not only educating and connecting the CLM community but rallying members to give back to the local community through service events in the process. Jason is also a frequent writer, speaker, and contributor for CLM events, and we are proud to honor him as our inaugural CLM Volunteer of the Year.”
Mr. Feld is a renowned nationwide construction claims leader who actively speaks at industry events. He serves as panel counsel for many prominent insurance carriers and provides personal counsel for multiple national and regional builders, developers, and contractors. With his vast experience and expertise, Mr. Feld is a trusted authority in the field and is highly regarded for his legal representation.
Read the full story...Reprinted courtesy of
Linda Carter, Kahana FeldMs. Carter may be contacted at
lcarter@kahanafeld.com
Navigating Threshold Arbitration Issues in Construction Contracts
April 29, 2024 —
Daniel D. McMillan and TJ Auner - The Dispute ResolverIncluding an arbitration clause in your construction contract may not mean that your dispute will be confined to arbitration. Instead, parties often find themselves in court litigating threshold issues related to the existence and/or enforceability of an arbitration clause. Common issues include whether the underlying contract containing the arbitration clause is valid, whether the dispute falls within the scope of the clause, whether the parties complied with contractual prerequisites to arbitration, whether issues related to arbitrability are decided by the court or arbitrator, and whether one of the parties has waived their right to arbitrate. This blog post highlights two recent construction cases addressing threshold issues that a party seeking to enforce—or oppose enforcing—an arbitration clause might face.
Seifert v. United Built Homes, LLC: Delegating Issues of Arbitrability to the Arbitrator
In Seifert, an owner sued a homebuilder in Texas federal court for breach of contract and sought damages and declaratory relief. No. 3:22-CV-1360-E, 2023 WL 4826206 (N.D. Tex. July 27, 2023). The builder moved to compel arbitration. The owner opposed and argued that: (1) there was no agreement to arbitrate because the underlying contract was null and void, and (2) its claim for declaratory relief fell outside the scope of the arbitration clause. The court did not address the merits of either argument. Instead, it determined that these were issues for the arbitrator to decide.
Reprinted courtesy of
Daniel D. McMillan, Jones Day and
TJ Auner, Jones Day
Mr. McMillan may be contacted at ddmcmillan@jonesday.com
Mr. Auner may be contacted at tauner@jonesday.com
Read the full story...